Government of Punjab · Punjab Energy Development Agency
Skip to Contentਪੰਜਾਬ ਊਰਜਾ ਵਿਕਾਸ ਏਜੰਸੀ
All projects
solar

Utility Solar Park - Rupnagar Phase 3

District
Rupnagar
Contractor
Bhullar Constructions
Budget
₹2209.3 Lakh
Timeline
2025-04-01 → 2026-03-31
Overall Progress37%
Milestones
DPR Approved
Tender Awarded
Site Handover
Construction 50%
Commissioning
COD Achieved
Health Score
72/100
Composite of schedule, budget & quality
ScheduleOn track
BudgetWithin ±3%
QualityA grade
Safety0 LTI