Solar Rooftop - Patiala Phase 10
District
Patiala
Contractor
Kaur Energy Solutions
Budget
₹838.0 Lakh
Timeline
2025-04-01 → 2026-03-31
Overall Progress11%
Milestones
DPR Approved
Tender Awarded
Site Handover
Construction 50%
Commissioning
COD Achieved
Health Score
64/100
Composite of schedule, budget & quality
ScheduleOn track
BudgetWithin ±3%
QualityA grade
Safety0 LTI