ev
EV Charging Station - Muktsar Phase 4
District
Muktsar
Contractor
Sukhbir Infra Pvt Ltd
Budget
₹1029.5 Lakh
Timeline
2025-04-01 → 2026-03-31
Overall Progress42%
Milestones
DPR Approved
Tender Awarded
Site Handover
Construction 50%
Commissioning
COD Achieved
Health Score
74/100
Composite of schedule, budget & quality
ScheduleOn track
BudgetWithin ±3%
QualityA grade
Safety0 LTI