All projects
hydro
Micro Hydro - Tarn Taran Phase 1
District
Tarn Taran
Contractor
Sandhu Renewables
Budget
₹2013.4 Lakh
Timeline
2025-04-01 → 2026-03-31
Overall Progress20%
Milestones
DPR Approved
Tender Awarded
Site Handover
Construction 50%
Commissioning
COD Achieved
Health Score
67/100
Composite of schedule, budget & quality
ScheduleOn track
BudgetWithin ±3%
QualityA grade
Safety0 LTI