Waste-to-Energy - Bathinda Phase 1
District
Bathinda
Contractor
Kaur Energy Solutions
Budget
₹2178.2 Lakh
Timeline
2025-04-01 → 2026-03-31
Overall Progress40%
Milestones
DPR Approved
Tender Awarded
Site Handover
Construction 50%
Commissioning
COD Achieved
Health Score
73/100
Composite of schedule, budget & quality
ScheduleOn track
BudgetWithin ±3%
QualityA grade
Safety0 LTI